Bumanik is delighted to announce the latest progress of its jetty which has reached the final stage of its construction. Thus far, the latest activities performed at jetty are piling and rehabilitating the edge of jetty which has been undermined by the tide.
Meanwhile, the trestle bridge, with the clear span of 500 meters, has been built and it is functioned as a platform that helps dump trucks to reach the barge on which the ore will be loaded.
The jetty itself is located in Solonsa Village and is 9,3 km far from the mining pit while the distance from jetty to EFO (Exportable Final Ore), in which the ore is going to be stored, is 400 meters. The EFO is ready to store the ore for shipment delivery. Approximately Bumanik will start its shipment activity in July 2018.